IEC 61850 Kategoria

First IEC 61850 Multivendor Project in the USA

wtorek, marzec 18th, 2008

An excellent group of TVA and vendor personnel made this Bradley project a success. Jim Kurtz, Manager of Protection and Control at TVA, had the following comments on the project: “I cannot stress how important collaboration like this is to the industry. For vendors and suppliers to work together to resolve issues will help not only them to provide a better product, but also to develop products that will meet the long term needs of the industry. While this effort has leaped TVA forward in technology, we still have work to complete.”The IEC 61850 substation communication standard is almost two years old. Worldwide, there are already over one hundred substations that have been commissioned and running with this new standard.

Several projects in North America have been implemented with IEC61850 by using products from a single manufacturer. This article reports on the status of a 500KV project - the first multi-vendor project in the United States to use this new standard.

The goal of the project is to utilize the new IEC61850 standard to its fullest (as practically possible) therefore confirming that the standard is much more than just a communication protocol. Interoperability, one of the major advantages of IEC61850, will be demonstrated. Our focus is not to describe or explain the theoretical background of the standard itself, but rather to show and demonstrate the practical use of an actual multi-vendor project and how the standard applies to protection engineers.

Substation Design & Layout
Another goal of this project is to eliminate or significantly reduce wiring between the relays, the control house and the breakers. The wires are replaced with the communication infrastructure fulfilling the requirements of the protection and control applications by exchanging IEC61850 GOOSE messages over Ethernet.

Protection & Control Scheme
Redundant protection, a TVA core protection requirement, is applied on all 500kV and 161kV transmission lines breakers and three single-phase 500/161/13kV power transformers within substation.

Transformer Protection
Two complete, comprehensive and independent transformer protection systems are implemented. Set “A” protection provides transformer differential protection, overcurrent protection, transformer sudden pressure protection, hot spot protection, LTC sudden pressure protection and restricted ground fault (RGF) protection for both neutral CT’s. Every transformer status and alarms, such as fan status, liquid levels, etc. are collected by the devices, which are located in cabinets mounted on each of the four single-phase 500/161/13kV transformers. Analog and digital data from the IEDs are available in IEC61850 format to the substation automation system.

Line Protection
Line protection relays provide distance/pilot protection, directional ground overcurrent, synchrocheck, breaker failure and reclosing. Additional pilot tele-protection devices are used for the Sequoyah 500 kV line (individual POTT schemes for both line protection relays) and the Conasauga 500 kV line (individual unblocking schemes for both line protection relays). Both line protection systems on each of the 161 kV lines will share a single communications device for their POTT schemes. Each line relay is operating in a breaker & ½ topology. (Fig. 2, Fig. 3)

Breaker Control
The substation contains redundant breaker control devices. The idea behind dual breaker control IEDs is to meet the same redundancy requirement as for line protection. The breaker control IED within the substation yard sends information to and receives information from the line relays using IEC61850 GOOSE messaging. (Fig. 4)

The only hardwire status input to each line relay is the breaker position statuses and this is only used if a digital IEC61850 state from either 52BCA or 52BCB devices are not available. A hardwire trip output from the line IED is wired directly to the breaker 1 and breaker 2 trip coils (for risk management purposes). With experience, future designs may provide the substation engineer the option to eliminate these hardwire inputs and outputs and to strictly use the GOOSE functionality.

Network Connections
All IEC61850 IEDs are connected via 100 MBps multi-mode fiber cables to substation hardened Ethernet switches located in the control house. VLANs are used within the IEC61850 GOOSE message configuration of each IEC61850 device to provide security within the network. Figure 9 shows a conceptual layout of the network.

Customer /Project Expectations
Since one of the goals of this multi-vendor project was to utilize the new IEC61850 standard to its fullest, it is clear that the customer had some key project expectations:

Open system for protection, control and data collection from any IED.
Interoperability between IEDs for protection and control functions. Ability to configure IEC61850 system with available manufacturer tools without need for on-site manufacturer support.
Comparable functionality with streamlined design. Eliminate panel control switches and lockout relays and incorporate functionality into IEC61850 IEDs. This dramatically reduces the panel layout design and allows for a smaller control house (about ½ the size vs. traditional design). For example, consider that just one set of protection, up to 12 breakers, can be protected and controlled using one single 19″ wide panel versus older designs with 1 breaker per panel with both Set A and Set B protection systems. Standard panel designs for any application can be created.
Accommodate multiple vendor IEDs
Comparable performance time
Secure & dependable overall system. Timely, secure flexible information transfers.
Flexible management/ operation
Economically viable solution
Common technology infrastructure
Reusable practices. Project established foundation of new substation practices oriented around IEC61850 and new procedures. Business case can be made for wholesale refurbishment with these new practices.
Effective data management system
Reduced wiring and installation costs. Besides the CT and PT wiring from switchyard breakers and motor operated disconnects, only breaker status and breaker trip wiring has been implemented. No inter-wiring exists between any of the IEC61850 IEDs.
High-speed local and remote downloads to IEDs over network
Improved Operations and Maintenance from remote and local monitoring and diagnostics via network to reduce service time
System health/status monitoring
Status communications between IEDs
Testing methodology. New test plan, tools and methodology needed to match systems new capabilities and plan to implement test cases. Ability to individually test any IED without the concern of operating other IEDs via the network.
On-Site LAB Workout Sessions & Configuration Tools Used
In August 2005, the TVA IEC61850 “project team” met for the first time (Fig. 6) to begin the process of designing the first IEC61850 based high voltage substation in the US. The team consisted of four major relay vendors and representatives from TVA’s relay and communication engineering departments. Besides all interoperability demonstrations organized previously by the UCA International Users Group or by CIGRE, the team’s objective for this project was to show that each relay vendor can demonstrate interoperability of the protection and automation devices from design to implementation in real life.

During the IEC61850 integration process the four relay vendors participated in three primary tests at the TVA “test lab” substation. The goal was to demonstrate that TVA could take the primary lead of configuring their substation with the available IEC61850 configuration tools using the manufacturers in a support role. This would be the first IEC61850 project where the customer would do the system engineering and IED integration. The integration during previous interoperability tests on other projects throughout the world had been implemented by members of the relay vendor’s development department using tools and programming language that were not always accessible or available for use by the customer. All participating vendors had previous experience with commissioning several IEC61850 based substation worldwide, but in almost all cases one of the vendors was the integrator and mainly used their own products, engineering tools and integration procedure to configure a substation. The integration of these previous projects was simpler because interpretation of the IEC61850 standard was uniquely confined to that vendor’s system architecture and product implementation. It is also important to note that trade show interoperability testing only covers a small portion of the functionality required for a complete substation solution. So, the TVA project in this respect was completely different from previous projects and the trade show interoperability tests. TVA was the system designer and system integrator and they would use the available tools from each vendor while at the same time deal with the unique interpretations of the new IEC61850 standard by each vendor.

Configuration Tools, ICD and SCD Files

The primary goal during the first test meeting (August 2005) of the “project team” was to configure all GOOSE links between the relays from the different manufacturers and to reach a minimal level of device interoperability. The procedure to achieve this is shown in Figure 1. All manufacturers had to supply an ICD file (IED Capability Description) that described the ability of the relays in a standard IEC61850 format. This ICD file is the interface between the relay manufacturers IEC61850 tools and the IEC61850 world. With the ICD files available, the customer can use any independent IEC61850 System Configuration tool to import the ICD files from each relay vendor and configure the system. (Fig. 7) Once the IEC61850 station is configured, a SCD file (Substation Configuration Description) can be created and exported describing the station in a standard IEC61850 format. The relay vendors must be able to use their proprietary tools to extract the information inside the SCD file and use it to configure the individual relays. TVA decided to use the only commercially available at the time IEC61850 station configuration tool with all the required functionality.

Lessons Learned & Testing Tools Used
During the first test meeting a significant amount of discussion was centered around the question of whether TVA wanted to use the GOOSE message implemented in UCA - called GSSE in IEC61850 to provide compatibility with UCA 2.0 implemented substations, or to use the real IEC61850 GOOSE message. After evaluation of all pros and cons, the decision was made to use the IEC61850 GOOSE message because of the advantages this new implementation has to offer.
Some discussions made it apparent that all relay vendors did not fully understand the power of the new standard. For example, it was thought that it was necessary to manually configure which information in a GOOSE message was to be sent first, the data information or the quality information. It was discovered that different manufacturers and, sometimes, different relays from the same manufacturer did it differently, so there was a fear that the information may get misinterpreted.

After a lot of discussions and phone calls, the team determined that the order of the information and quality data did not matter as long as it was declared in the ICD file. The receiving relay will get the information because it is defined via the SCD file and it knows how to process the information correctly.
During that meeting most relay vendors also did not have their tools ready to automatically export and import from their proprietary programming tools to the IEC61850 world via ICD and SCD files. This resulted in a significant amount of manual programming work. To validate the correctness of the ICD file, the team used the System Configurator as well as the IEC61850 Validator tool. It was determined initially that some of the ICD files had some format errors and during the import of the files, an IEC61850 Validator tool produced error reports.
These errors were the first hurdle that had to be resolved.
Even though the validation of the ICD files could verify the correct syntax of the file, it could not check for the semantics. Once we were able to import the ICD files and use the System Configurator tool to configure the required system, in some cases, we were not able to receive the programmed GOOSE message because the GOOSE message description was different than what was actually described in the ICD file. To analyze problems where one relay vendor claimed that they were sending a GOOSE message that the receiving vendor did not receive, the team used the network protocol analyzer tool Ethereal® with the MMS decoder functionality. Ethereal® allowed for the entire GOOSE structure to be displayed, so that a view of the specific relay IED including the value of the data and quality information could be analyzed.
By using Ethereal®, we were able to see where adjustments were necessary and finally all GOOSE messages were sent and received correctly between IEDs of the different manufacturers. The goal for the test week was achieved and the concept of IEC61850 was proven powerful. Even with this accomplished, configuration of the TVA system was not simple. However, the tools available would allow the customer to configure the system by themselves. During the design process, there were several firmware updates, patches and discussions between the development departments of each of the relay manufacturers. Without the great teamwork between all the manufacturers and the deep knowledge of the implementation details of IEC 61850, the interoperability goal could not have been achieved. But it was clear that this was not a practical procedure that a utility could use to configure their IEC 61850 substations.
The second test week was conducted in January 2006. The goal was to have TVA be the system designer/ integrator and configure the system with as little as possible support from the relay manufacturers. We have to admit that this goal was not achieved, because some of the manufacturers’ tools were still not mature enough. A lot of manual work was still required and detailed knowledge of IEC 61850 was also necessary in order for the correct ICD files to be extracted out of the SCD file for configuring each IED. With support of the relay manufacturers, the system was successfully configured and working at the end of the week, but the actual goal was not achieved. At the end of the meeting TVA requested that each relay vendor finish their tools, so that they can have the capability of configuring an IEC61850 system independent of the relay manufacturers.
All manufacturers met again in the TVA “test lab” substation in the third test week (March 2006). Focus was now on the tools of the manufacturers and if they were able to support TVA in configuring their IEC 61850 substation without any major support from the relay vendors and a need to have deep knowledge of the IEC 61850 implementation details.
The tools from ABB, GE Multilin and Siemens were found mature enough to fulfill the customer requirements. However, a new problem was discovered regarding different tools supporting different optional features of the IEC 61850 standard. For example, some IEDs need to know some hierarchical data like “voltage level”, “feeder name” in each IED. This data can be submitted to the IEC 61850 system configurator via the SSD files (System Specification Description). This file format is optional in IEC 61850 and doesn’t have to be implemented. The used system configurator in this case did not support this feature at this time. This made it necessary that after the SCD file was created by the system configurator that the file was edited by another tool to add this hierarchical data and then re-imported in the system configurator.
At the end, TVA was able to develop a procedure that allowed them to configure and design the system independently, without on-site support from the different relay manufacturers. This was demonstrated by TVA during the preparation for the May 2006 IEEE T&D show in Dallas, TX where the Bradley project configuration proved interoperability in the UCA International Users Group IEC 61850 demonstration.
TVA built the demonstration panels and configured the system that was placed on display at the show using the IEC 61850 tools provided by each vendor.
Overall, the process involved a number of hurdles, but demonstrated that by having a strong and determined team of relay manufacturers and excellent group of TVA engineers, future IEC 61850 project implementations can be successful and economically advantageous.

Lessons Learned Throughout the Project
This project was a tremendous learning experience for the participating vendors and TVA. In addition to those described in the on-site lab workout, the following are some of the additional lessons learned throughout the project.

VLAN issue with Ethernet switch - The Virtual LAN (VLAN), an advanced layer 2 function defined in IEEE 802.1Q, provides high priority tagging of a message and efficient means for data exchange in applications using the IEC61850 station bus and process bus profiles. In the IEC61850 standard, a VLAN tag was defined as part of a valid GOOSE message. Some vendors’ IED implementation required the VLAN tag in a received GOOSE messages to validate the information. The Ethernet switches used in the Bradley project initially did not pass the VLAN priority tag through the switch. This issue was identified early in the project and a firmware update was provided for the Ethernet switches.

Logical device names - Logical Device (LD) naming syntax is defined in IEC 61850 part 7-2. The logical device names in this system were to be named according to the customer’s standard practice for devices associated with breakers. The “99A” and “99B” breaker identification labels were preferred since this was TVA’s standard for naming multifunction microprocessor based relays. The naming syntax restrictions defined in the IEC 61850 standard does not allow these type of LD names (those starting with a number) due to constraints in MMS (Manufacturing Message Specification).
The solution for this issue was to name the breaker IEDs (Logical Device names) “LA99A” and “LA99B” respectively.

GOOSE ID naming - GOOSE ID naming is an attribute that is contained in the GOOSE message. One IED vendor uses this GOOSE attribute to display status of received GOOSE messages. In the Bradley project’s system engineering tool, the GOOSE ID was automatically assigned as a number, although the standard is not restrictive to numbers and allows strings.
The issue on utilization of IEC 61850 data is that one vendor usage or extension of the data may not be possible with another vendor’s implementation.
The GOOSE ID strings in the SCD file were renamed using a separate tool capable of manual modification of GOOSE ID names.

Status vs. quality order - It was thought that it was necessary to specify which information in a GOOSE message was to be sent first, the data information or the quality information. It was discovered that different manufacturers and sometimes different relays from the same manufacturer did it differently, so there was a fear that the information may get misinterpreted. After a lot of discussions and phone calls, the team determined that the order of the information and quality data did not matter, as long as it is declared in the ICD file. The receiving relay will get the information because it is defined via the SCD file and it knows how to process the information correctly.

The effect of the quality state on the status state - Conventional hard wiring states are either on or off without an indication of signal quality. The IEC 61850 standard does not provide rules for the interaction between quality and status bits. The question posed is should the loss of the quality state effect the state of the status value, thus a quality state of 0 results in a force of status state of 0 (even if the status is actually true or 1)? Or should a quality state of 0 result in staying at the last known status state (which is 1 in this example)?

Both vendors meet standard, but do not interoperate - Device (IED) conformance to the standard is accomplished by validating an IED at an accredited IEC 61850 test facility in accordance to the IEC 61850 Part 10 and the UCA International test procedures. It is important to note that the conformance testing does not validate conformity but only validates the IED testing has identified no “non-conformities”. An IEC 61850 device certificate is then issued by the accredited test facility providing the vendor a statement that no non-conformities were identified during the IED testing. The testing is limited to a single device in a test system and does not cover multi-device system level testing or interoperability in a multi-vendor system, i.e. the IEC 61850 certificate does not guarantee that a certified device will interoperate with another device. Device and client interoperability has been left to the vendors to validate. In the Bradley project, all vendors had IEC 61850 certified IEDs, but several issues as previously mentioned resulted from wrong interpretation or ambiguity in the IEC 61850 standard. Below are some examples of issues encountered during the Bradley project that impacted GOOSE interoperability between different vendor devices:

Supporting optional attributes in GOOSE - One example of the interoperability issues encountered was that one vendor could include both mandatory and optional attributes in the IED using GOOSE messaging. Then another vendor’s IED (GOOSE receiver) could only understand mandatory attributes and was not able to support the optional attributes; thus preventing interoperability. The resolution was to not use the vendor specific attributes in the GOOSE communication between these IEDs.

Adherence to name case sensitivity - Another issue encountered was in the adherence lower and upper case sensitivity. One vendor was more liberal and did not strictly adhere to the case sensitivity as defined in the standard. The other vendor’s engineering tool was rejecting the names when the case was opposite to that as defined in the IEC61850 Part 7. This was resolved by using a newer version of the SCL XML schema.

Quality in GOOSE versus no quality - The support of data item quality flags in GOOSE datasets was a major obstacle in the beginning of the Bradley project. Different vendors provided different levels of support for quality flag data. In this case, one vendor required quality information in their application to confirm validity of the data for each value received via GOOSE. At the same time, another vendor was not able to send quality information in the GOOSE message. This resulted in the inability to exchange GOOSE message between IEDs and thus, a major interoperability issue. It was decided to use both status and quality within the Bradley project for consistency. Both quality and status are now available in each vendor’s device and successful GOOSE interoperability between multiple vendors has been accomplished.

Length of names of GOOSE Control Blocks - The length of GOOSE control block names supported in the different vendor IEDs was an issue. The Bradley project’s system engineering tool automatically generates names for DataSets and GOOSE Control Blocks. The string length of these automatically generated names was too long for one vendor’s IED. The GOOSE Control blocks in the SCD file were renamed using a separate tool capable of manually modifying the GOOSE control block names.

Substation section - The substation section of a SCL file contains information about the substation layout, logical node references and device configuration and association information. One vendor’s IED tool required this substation section along with the Logical Node references to be imported from SCD file generated by the system engineering tool. The system engineering tool was not able to produce the needed information so manual manipulation of the SCD files was required to complete the IED engineering. The resolution was manual configuration of the SCD file adding the necessary information.

What vendors have to improve to make it easier? - Better preparation of the product and system technology is needed. IEC 61850 is a very comprehensive and complex standard that has the potential to revolutionize substation automation systems if the necessary tools and product functionality is available. The vendors involved in this project needed to collaborate to assure that the substation automation system functionality and interoperability capabilities were validated prior to the execution of the customer engineering and system build up.

What could have been done differently? - Clearly, the lessons learned in the multi-vendor TVA Bradley IEC 61850 substation project have been extremely valuable for the entire industry pushing for this new standard. The extent of the Bradley project provides complete functionality, with a goal to move into the digital substation.We can state that the Bradley project has explored all benefits made possible through the new standard that prior to this project has not been done in a multi-vendor environment. Most of the executed IEC 61850 projects have been turnkey homogenous vendor solutions where interoperability between one vendor’s products is much easier. In the other projects where multi-vendor projects have been executed, the foreign device has typically been a main 2 or backup protection terminal where the system functionality only required limited exposure of the IED functionality via the IEC 61850 system. On the other hand, industry expositions demonstrating multi-vendor IEC 61850 interoperability have set expectations that the complete IEC 61850 benefits are readily available. This is not the case since these demonstrations focus on simplistic applications and minimal functionality to prove vendor A can interoperate with vendor B.

What could have been done in this project is to set up an interoperability project to validate product and system functionality before starting the Bradley project. In this case, the project was conducting the interoperability validation. System engineering is the critical step in the Bradley project where an open discussion regarding system engineering tool to know the limitation in the integration of other vendor’s IEDs. The system engineering process is one area that multi-vendor exchange of IED and engineering data needs improvements. Today, a vendor’s system engineering tool works perfectly with their own devices but creates limitation when exposed to other vendor’s devices.

What needs to be done in the industry is a higher level of interoperability functionality and standard test cases that can assure a minimum level of interoperability. Here the recommendation is that the UCA International Users Group set up performance and functionality criteria for levels of interoperability. Device level conformance certification only validates a fraction of the overall substation automation capability. Figure 8 shows the final design deployed for the TVA Bradley Substation.

The industry should consider Ethernet switches as “protective devices” when it comes to implementations of critical protection schemes using IEC61850 standard and whether they are configured and maintained by protection/test engineer or IT department.

IEC 61850 SCL Manager Details

poniedziałek, marzec 17th, 2008

Key Functionality
System Specification

The system specification as per IEC 61850 covers definition of complete electrical system interconnections (SLDs) required for a substation and defining the functionalities (Logical Nodes) that need to be performed by each element or group of elements together. Creating substation specification in SCL Manager involves the following steps

Draw complete SLD using the graphical interface available in SCL Manager. This involves creation of substation elements and its interconnection using connectivity node (point or bus-bar).

Choose the functionality required on each element of substation which is done by selection of suitable Logical Nodes (LNs) from the list of logical nodes.

Save the complete system specification as System Specification Description (.SSD) file.

Substation Configuration

The substation configuration consists of linking the functionality elements described in the system specification to the actual functional points (LNs under the IEDs) & description of complete communication schemes. Following steps are needed in SCL Manager for completing the Substation Configuration.

Load the file containing complete system specification (.SSD) or create the complete specification using system specification feature.

Create IED sections which are needed for the substation.

Import the specific ICD to each IED section & define the communication attributes for the specific IED. This will create the actual data and functional points for the complete substation.

Link the substation functionalities defined in the specification to the actual functional points. It is achieved by linking the LNs available in the substation elements to the LNs of loaded IEDs.

Save the complete substation configuration in Substation Configuration Description (.SCD) file.

IED Capability Description

This functionality is required if SCL Manager is used to configure any new vendor device which does not have an ICD but will completely work depending on the configuration file created as per SCL standards. This is especially applicable for Protocol Gateways having IEC 61850 server and a user configuration file as per SCL are required for its suitable working. This is also applicable for IEC 61850 implementation in an already existing IED. The ICD file of the device for system configurator and CID file that need for the device can be generated from Kalki SCL Manager which requires the following steps.

Define an IED section.

Create separate logical divisions (LDs) within the physical device as required based on the application & add mandatory functions (LNs - LLN0 & LPHD) with required data & attributes under each logical divisions. E.g.: A physical device related to the protection can have logical divisions of measurement (MEAS), protection (PROT) and disturbance (DIST).

Add other functionalities (LNs) related to the logical division by choosing the same from the template and select the required data & attributes. E.g.: Measurement logical division can have MMXU, MMXN, MDIF LNs , Protection logical division can have PTOC, PDIF, PTEF LNs and disturbance logical division can have RDRE, RADR, RBDR LNs.

Assign /change the default values for various elements like control model by adding / editing data object instances (DOI) under each logical nodes.

Create required data sets under each logical device and attach data to the same from different LNs using FCDA.

Define required Report Control Blocks under each logical node and attach the relevant data set to the same.

Define required GSE control blocks under LLN0 and associate the suitable dataset to the same.

Save the file as .ICD / .CID as per the requirement.

Mapping external signals

Mapping external signals involves the mapping of source data coming through control blocks like GSE, RCB to destination data points available under logical nodes of different IEDs. Mapping of external signals requires the following steps.

Load the file containing complete substation configuration (.SCD) having multiple IED sections & choose option for mapping external signals.

Source Selection — Select the source IED, type of data transfer (GSE, RCB or Specific LN) & choose the data tag coming under GSE, RCB or LN.

Destination Selection — Map the specific tag to the destination logical node. Select destination IED, LN and choose automatic or manual entry for the destination identifier.

Save the complete mapping as part of .SCD file itself.

Other Functions

The other functionalities available in Kalki SCL Manager are as follows.

Validate SCL files - User can validate any SCL file (SCD, SSD, ICD or CID) by just choosing validate option and selecting the file. The validation results are logged into separate window indicating the complete details of failures.

Generate Communication / equipment Tags - User can generate complete communication / equipment tags from loaded SCD / SSD files. It can be saved to files which can be used for client applications.

File Types

SCL Manager allows user to create the following file formats as defined in IEC 61850 standards.

IED Capability Description (.ICD) File. It defines complete capability of an IED. The file contains a single IED section, an optional communication section and an optional substation part which denotes the physical entities corresponding to the IED.

System Specification Description (.SSD) File. This file contains complete specification of a substation automation system including single line diagram for the substation and its functionalities (logical nodes). This will have Substation part, Data type templates and logical node type definitions but need not have IED section.

Substation Configuration Description (.SCD) File. This is the file describing complete substation detail. It contains substation, communication, IED and Data type template sections. An .SSD file and different .ICD files contribute in making an SCD file.

Configured IED Description (.CID) File. It is a file used to have communication between an IED configuration tool to an IED. It can be considered as an SCD file stripped down to what the concerned IED need to know and contains a mandatory communication section of the addressed IED

Protection Automation and Control Magazine

poniedziałek, marzec 17th, 2008

Protection Automation and Control Magazine pacworld first edition for summer of 2007 has been published. Spearheaded by Alex Apostolov, this magazine promises to be bring more active and open discussion about IEC 61850 and Protection, Automation and Control in general. The industry do indeed need an avenue for technical and expert discussions and opinion makers to bring out their points of view on the current and future challenges it faces.

In his editorial for the first edition, Alex talks about how the IEEE transactions used to have questions and comments on every paper and the authors comments on the same at the end of the paper. He mentions how behind the iron curtain a few decades back as a young protection engineer it gave Alex a global view and meaningful sense of these transactions and the context in which the paper needs to be seen. Now this is no longer a practice that IEEE transaction follows. As he rightly says in all the limited conferences on this subject globally, due to paucity of time and the busy schedule of the modern day world and its intent on accommodating as many things as possible in a very short time, there is no more open discussions and debate on most topics that concern the protection, automation and control engineers of today.

He mentions this to be one of the key objectives of pacworld. However, in addition to discussions and awareness building, it is also important to address some of the other burning facts like increasing academic and research interest in power systems such that more new students opt for these courses, as well as to involve and upgrade the technical knowledge and awareness of the main stream utility engineers and power system experts in the new technology developments in this space.

I believe these objectives to be a very noble and right intent and if this intent is kept alive and remains the driving force of the magazine in the days to come, it shall surely be a great point of convergence of thoughts and minds of the Industry and shall be a must read for all.

IEC 61850 is expanding its horizons

poniedziałek, marzec 17th, 2008

Its been quite some time before i myself remembered about this blog. I have been busy creating another one at . However it did not look good that a blog can be in the company website and that is when i re-discovered this blog.

Anyway, much water has flowed since this blog was started. IEC 61850 has become a more complete standard, there seems to be a general consensus on IEC 61850 across the Atlantic, even though the adoption levels vastly differ. A great news in adoption has been the enthusiasm shown by developing countries like India / China.

However, the big news is the efforts at the standardization level to find new meaning and use for the standard from being a standard and model within the substation to expanding its scope, depth and breadth across substations and trying to integrate with old and new standardization efforts in other committees. However, i am sure there are differing views on this and hope to see some discussion on this here.

IEC61850 - Long way to go

poniedziałek, marzec 17th, 2008

I do agree with the point that IEC61850 is and will be expanding its horizons especially after redefining its scope from Substations to complete power utility. With object models of Wind and Hydro already available & models of DER, standards of substation - substation and substation - control centre communication & mapping to web services are already underway, it will find a completely different focus. We can even expect revolutionary changes after the possibility of SCL to migrate to CIM to provide complete models needed for an EMS/ DMS systems.

But looking back, can we say that objectives of IEC61850 are completely achieved? Can we say the IEC61850 devices are completely interoperable? I feel that many vendor implementations had made this standard to deviate from its objectives. IEC61850 had provided options for private LNs, data & GGIOs for handling the situations which cannot be handled by the standard models. But now the scenario had reached in such a level that all the vendors are finding it much easy to have private models rather than going for the standard LNs, data or formats which will not help in achieving goals of a global standard. What is the purpose of the total interoperability, if a vendor IED cannot accept a GOOSE because there is a time stamp element? Are the test certificates and interoperability events helping any bit in providing true inter-operability? I feel interoperability still remains a key issue in migrating to IEC61850.

Another area I want to point out is the engineering efforts for IEC61850 which was hyped to be much less comparing with the native mechanisms. But if we notice the tools and systems available for engineering IEC61850 today, it is much oriented on the standards rather than looking from the users’ angle for the configuration. The user has to follow complete & elaborate 61850 standards to achieve the complete configuration. The second is the dependability of vendor tools for configuration is too high that each user needs to know all the vendor tools to achieve even simple configurations like GOOSE mapping. So the current scenario is such that IEC61850 has increased the engineering efforts rather than reducing the same, if one were to do an independent engineering based on the standard.

I personally feel TC57 WG10 had never foreseen such a huge welcome for IEC61850 which made the standard to have some limitation. The standard could have been made with Substation configuration language (SCL) completely compatible with the UML based CIM models. Today, with all implementations working well with the SCL & problems in migrating to CIM, it will require a long way for sending the model information to EMS/DMS systems.

In spite of all these problems, the high benefits in using the standard in comparison with native protocols, is driving the same a long way through. Tissues (technical issues) forum for IEC61850 had come good for the standard which takes users opinion and problems to address the same in revisions. Let’s hope new revisions can throw some light to these problems & come up with effective ways to ensure the interoperability.

IEC 61850

wtorek, marzec 4th, 2008

Standard IEC61850 bazuje na ogólnym modelu funkcji automatyki
stacyjnej. Definiuje on zestaw standardowych interfejsów, przez
które przepływają dane. Interfejsy te są nazywane węzłami logicznymi
i pełnią dla danej funkcji rolę „okna na świat”. IEC61850 jest
jedynym standardem, który obejmuje wszystkie trzy poziomy komunikacji
na stacji elektroenergetycznej: poziom stacji, poziom pola
oraz poziom procesu. Dotychczasowe protokoły i standardy znajdują
zastosowanie w jednym lub najwyżej dwóch z wymienionych
poziomów komunikacji na stacji. Bierze się to stąd, że większość
używanych protokołów było tworzonych i rozwijanych z myślą
o wąskim wycinku zastosowania.
IEC61850 promuje wykorzystanie Ethernetu zamiast komunikacji
typu master-slave. Zaletami takiego rozwiązania są:
_ W sieci Ethernet każde urządzenie IED (Inteligent Electronic
Device) może wysyłać informacje w dowolnym czasie. Nie ma
urządzenia nadrzędnego „Master”, które zarządza przydziałem czasu
komunikacji. Urządzenie „Master” jest podstawą rozwiązań typu
Master-Slave. Gdy ono zawiedzie, niemożliwa staje się jakakolwiek
dalsza komunikacja wszystkich urządzeń „Slave”.
_ Dystrybucja informacji poprzez IED odbywa się w trybie „multicasting”
(urządzenie wysyła informację równolegle do wielu odbiorców),
co znacząco poprawia wydajność – szczególnie w odniesieniu
do informacji, dla których czas przesyłu jest czynnikiem krytycznym.
_ IEC61850 realizuje transfer danych poprzez sieć opartą na protokole
TCP/IP. Dane innych standardów – bazujących również na
Ethernecie i TCP/IP, takich jak WEB-SERWER lub transmisja danych
dla celów eksploatacyjnych, mogą być przesyłane równolegle,
wykorzystując tę samą infrastrukturę komunikacyjną.
Wszystkie urządzenia zgodne z IEC61850 są kompatybilne, dzięki
czemu nie ma potrzeby stosowania urządzeń gate-way do komunikacji.
Kompatybilność została osiągnięta dzięki określeniu przez
standard IEC61850 tzw. języka SCL (Substation Configuration
Language). W rezultacie pliki ICD opisujące urządzenie IED w zakresie
komunikacji oraz plik SCD opisujący konfigurację całej stacji
(w zakresie wymiany danych pomiędzy urządzeniami), są tak samo
czytelne dla wszystkich wytwórców.
W odróżnieniu od innych, IEC61850 jest jedynym tak otwartym
standardem. Jeżeli w przyszłości nastąpią zmiany w technologii komunikacyjnej,
adaptacja w urządzeniach zgodnych z IEC61850 będzie
minimalna. Tymczasem w dotychczasowych protokołach taka
zmiana może prowadzić do ich zaniku, na korzyść innych nowych
protokołów.